§ 77.215. Refuse piles; construction requirements.
358 words·~2 min read·
/us/cfr/t30/s§ 77.215·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(a)Refuse deposited on a pile shall be spread in layers and compacted in such a manner so as to minimize the flow of air through the pile.
(b)Refuse shall not be deposited on a burning pile except for the purpose of controlling or extinguishing a fire.
(c)Clay or other sealants shall be used to seal the surface of any refuse pile in which a spontaneous ignition has occurred.
(d)Surface seals shall be kept intact and protected from erosion by drainage facilities.
(e)Refuse piles shall not be constructed so as to impede drainage or impound water.
(f)Refuse piles shall be constructed in such a manner as to prevent accidental sliding and shifting of materials.
(g)No extraneous combustible material shall be deposited on refuse piles.
(h)After October 31, 1975 new refuse piles and additions to existing refuse piles, shall be constructed in compacted layers not exceeding 2 feet in thickness and shall not have any slope exceeding 2 horizontal to 1 vertical (approximately 27°) except that the District Manager may approve construction of a refuse pile in compacted layers exceeding 2 feet in thickness and with slopes exceeding 27° where engineering data substantiates that a minimum safety factor of 1.5 for the refuse pile will be attained.
(i)Foundations for new refuse piles and additions to existing refuse piles shall be cleared of all vegetation and undesirable material that according to current, prudent engineering practices would adversely affect the stability of the refuse pile.
(j)All fires in refuse piles shall be extinguished, and the method used shall be in accordance with a plan approved by the District Manager. The plan shall contain as a minimum, provisions to ensure that only those persons authorized by the operator, and who have an understanding of the procedure to be used, shall be involved in the extinguishing operation. (Secs. 101, 508, Pub. L. 91-173, 83 Stat. 745, 803 (30 U.S.C. 811, 957), Pub. L. No. 96-511, 94 Stat. 2812 (44 U.S.C. 3501 et seq.)) \[36 FR 9364, May 22, 1971, as amended at 40 FR 41776, Sept. 9, 1975; 60 FR 33723, June 29, 1995\]
Connections20 cite this · traces to 2
Cited by 20 sections · top 13
register
- NoticesRequest for public comments
- NoticesNotice
- NoticesNotice of request for public comments
- NoticesRequest for public comments
- Rules and RegulationsFinal rule
- Rules and RegulationsFinal rule
- Rules and RegulationsFinal rule
- NoticesMeeting notice
- NoticesNotice of availability; request for comments
- NoticesNotice
- Proposed RulesNotice
- NoticesRequest for public comments
- NoticesProposed rule; public comment period and opportunity for public hearing
Traces to 2 documents
4 references not yet in our index
- Pub. L. 91-173
- 83 Stat. 745
- Pub. L. 96-511
- 94 Stat. 2812
Citation graph
cites case law
§ 77.215
Refuse piles; construction requirements.
Fed. Reg.×20
Pub. L.Pub. L. 91-173
Stat.83 Stat. 745
Pub. L.Pub. L. 96-511
Stat.94 Stat. 2812
Cites 6Cited by 20 across 1 source